Machinery Orders Are Up 13.7% This Year. The Install Work Comes Next

Census data show US machinery orders rose for the 21st time in 22 months in October and are 13.7% ahead of last year. The equipment now on order will need contractors to install it and a service plan to keep it running, and both are already stretched.

November 27, 2026·Operations Leadership
A white gantry machine with cable carriers and a servo motor working over a flat production table in a brightly lit modern factory

Key Takeaways

  • US machinery orders rose 1.8% to $46.8 billion in October, their 21st increase in 22 months.
  • Unadjusted machinery orders for January to October total $443.3 billion, 13.7% ahead of the same period last year, and the machinery backlog stands at $156.7 billion.
  • 88% of construction firms with craft openings say those roles are as hard or harder to fill than a year ago, and 42% say worker shortages have delayed projects.
  • Only 44% of 500 US operations, procurement and safety leaders have real-time visibility into third-party workforce and safety risk.

The headline durable goods number on Wednesday was unremarkable: orders up 0.2% in October. Underneath it sat one of the steadiest signals in the factory economy. Orders for machinery rose again, as they have in all but one month for nearly two years, and they are running well ahead of what machine builders are shipping. For operations leaders, that backlog is not an abstraction. Every unit in it is a machine that will one day arrive at a plant on a truck and need riggers, electricians, start-up technicians and a parts and service plan before it makes a single good part.

Orders Keep Running Ahead of Shipments

The Census Bureau's advance report on durable goods, released on November 25, shows new orders for manufactured durable goods rising $0.8 billion, or 0.2%, to $346.7 billion in October. Machinery, which the bureau says has risen in twenty-one of the last twenty-two months, drove the increase, climbing 1.8% to $46.8 billion. Machinery shipments rose more slowly, by 0.5% to about $45.1 billion, so orders outpaced deliveries again and the machinery backlog grew 1.1% in the month to $156.7 billion.

The longer view is sharper. On an unadjusted basis, machinery orders for January to October total $443.3 billion against $389.8 billion a year earlier, a gain of 13.7%. Across all nondefense capital goods, new orders rose 0.8% to $109.4 billion in October while unfilled orders rose 1.2% to $980.6 billion. These figures are not adjusted for inflation, so part of the gain is price rather than volume, but the direction is plain: industrial buyers have committed to a large volume of equipment that has not yet been delivered.

Much of that equipment will land in 2027. The next advance report is due on December 23, but no single month will change the planning task. A plant expecting new machinery next year is, in effect, scheduling a construction and commissioning project inside a running operation.

The Crews That Install It Are Scarce

Installing a machine is skilled trade work: rigging and setting, anchoring, power and controls wiring, piping and guarding. Plants rarely keep all of that in house, so they draw on the same contractor labour pool as the construction industry, and that pool is tight. The 2026 Workforce Survey from the Associated General Contractors of America and NCCER, which drew 1,830 respondents in July and August, found 87% of firms with openings for hourly craft positions. Among firms with those openings, 88% said they were as hard or harder to fill than a year earlier, and half of respondents said available candidates lacked the skills, certificates or licences the work requires.

The delays are already visible. Forty-two percent of respondents said shortages of their own or their subcontractors' workers had delayed projects, the most commonly cited cause, and 74% had experienced at least one significant delay in the past year. Data centres are adding to the pull: of firms that had worked on one, 58% said those projects had increased competition for skilled workers. "The need for people to work on new data centers is keeping labor conditions tight," said Ken Simonson, the association's chief economist. A plant that books its installation crew late is competing for the same electricians as a hyperscale build.

Scarcity also changes who turns up. When preferred contractors are booked, work flows to second-tier firms and their subcontractors, often people who have never been through the plant's own qualification process. Avetta research fielded by Censuswide in June among 500 US senior leaders in procurement, supply chain, operations and safety found 77% reporting rising supply chain and workforce risk over the past year, while only 44% had real-time visibility into third-party workforce and safety risk. Sixty-eight percent had already experienced operational delays or shutdowns tied to that risk. An installation is precisely the moment when several unfamiliar crews are lifting heavy loads and making live connections beside running lines.

The Service Contract Outlasts the Install

The commissioning date is the start of the machine's life, not the end of the purchase. Machine builders know it. Research from Syncron, summarised by the Association of Equipment Manufacturers, drew on more than 550 OEM leaders across North America and Europe and found that 80% plan to increase aftermarket investment over the next five years, with nearly half citing it as a top strategic priority. The piece was written by Syncron, which sells aftermarket software, but the direction it describes is consistent: OEMs increasingly expect parts and service to carry their margins.

For the buyer, that means the terms agreed at the point of order (recommended spares, parts pricing, remote support, response times and access to service data) shape running costs for a decade. Those terms are easiest to negotiate while the order is still open and the machine builder still wants the deal. Once the machine is installed and the plant depends on proprietary parts, the leverage has moved.

What Operations Leaders Should Do Now

A full order book for machine builders is a full project calendar for the plants that will receive the machines. The work that decides how quickly new equipment earns its keep can start well before it ships.

Machinery orders have now risen in twenty-one of twenty-two months. The plants that treat that backlog as a project pipeline, with crews, qualifications and service terms lined up in advance, will turn new equipment into output soonest. The rest will find the machine has arrived and the people to install it have not.